/Water/Cork Non-domestic Water Metering – D&B and O&M
Mainline was the sole supplier to Cork County Council to design, build and install 20,000 non-domestic water meters in Cork. The Design & Build (D&B) contract was completed in 2010. In conjunction with this, Mainline Operates and Maintains (O&M) the 20,000 non-domestic water meters on behalf of Cork County Council / Irish Water. The O&M contract commenced in 2006 and continues until 2021. Under the O&M contract, we read, repair and maintain all 20,000 meters, as well as manage all other aspects of the water meter infrastructure, including identification of new Customers, surveying and new meter installations. The O&M project also deals with the capital replacement of the 20,000 installed meters, all of which were replaced between 2016 and 2019.