Hastkullen Wind Farm Sweden – EBoP

We successfully delivering the 73 Wind Turbine Electrical Balance of Plant (EBoP) for Hästkullen Wind Farm, in the Nysäter wind park, close to Sundsvall. The scope of the project included:

  • Engineering and construction (design, optimisation and build) of the 36kV collector cable to 73 wind turbines.
  • Over 95 km of associated civil works, trenching and backfill, through a variety of terrains from wetlands to rock, including a number of directional drills.
  • Over 95 km of associated earthing conductor works.
  • Over 155km of fibre telecommunication works.
  • Installation, cable jointing, testing, commissioning and energisation of almost 455 linear km of 36kV cable.
  • Various additional civil works, including the construction of an access road.